Three processes arrive at time zero with CPU burst times of 0.01 seconds, 15 milliseconds, and 25 milliseconds. If the scheduler uses Non-Preemptive Shortest Job First (SJF), what is the minimum achievable average waiting time in milliseconds (rounded to 2 decimal places)?
11.67
Step-by-Step Solution
Key idea: Convert all burst times to the same unit, then apply SJF to minimize average waiting time.
Step 1: Convert all burst times to milliseconds:
- : 0.01 seconds = 10 ms
- : 15 ms
- : 25 ms
Step 2: Sort by burst time (SJF order):
- : 10 ms
- : 15 ms
- : 25 ms
Step 3: Calculate waiting times:
- : WT = 0 (runs first)
- : WT = 10 (waits for )
- : WT = 10 + 15 = 25 (waits for and )
Step 4: Calculate average waiting time:
Answer: 11.67