An IT project has exactly 4 weeks remaining and a fixed budget. The team consists of 4 developers and 1 project manager (who cannot code).
Constraints:
- Each developer can work a maximum of 50 hours per week.
- Company policy mandates that 20% of every developer's total weekly hours must be spent on documentation.
- A new critical feature requires exactly 700 hours of pure coding time to be completed within the 4 weeks.
Proposed solutions to meet the coding requirement:
- Hire 1 external contractor for the 4 weeks at 40 coding hours per week (contractors are exempt from the documentation policy).
- Negotiate with management to reduce the documentation mandate to 10% of total weekly hours for all 4 developers.
- Require 2 developers to work 60 hours per week for the 4 weeks to cover the deficit.
- Extend the project deadline by 1 week (5 weeks total), but the client insists documentation must now be 25% of total weekly hours.
How many of the above proposed solutions are mathematically feasible to deliver the required 700 hours of coding work within the revised constraints?
C
Step-by-Step Solution
Key idea: This is a "resource management under constraints" question, recognizable because it requires calculating maximum feasible output against a fixed demand while respecting multiple overlapping rules.
Step 1: Calculate baseline capacity.
Max hours per developer per week = 50.
Documentation = 20% of 50 = 10 hours.
Max coding hours per developer per week = 50 - 10 = 40 hours.
Total baseline coding capacity = 4 developers × 40 hours/week × 4 weeks = 640 hours.
Deficit = 700 - 640 = 60 hours.
Step 2: Evaluate each proposed solution.
- Solution 1: Adds 1 contractor × 40 hours/week × 4 weeks = 160 coding hours. Total capacity = 640 + 160 = 800 hours. (800 ≥ 700) → Feasible.
- Solution 2: Documentation = 10% of 50 = 5 hours. Coding = 45 hours/week/dev. Total capacity = 4 × 45 × 4 = 720 hours. (720 ≥ 700) → Feasible.
- Solution 3: Requires 60 hours/week, which violates the hard constraint of "maximum 50 hours per week". → Infeasible.
- Solution 4: Duration = 5 weeks. Documentation = 25% of 50 = 12.5 hours. Coding = 37.5 hours/week/dev. Total capacity = 4 × 37.5 × 5 = 750 hours. (750 ≥ 700) → Feasible.
Step 3: Count feasible solutions.
Solutions 1, 2, and 4 are feasible. Total = 3.
Answer: 3