In a time and work problem, if the number of workers changes midway through the job and their daily working hours also change, which standard quantity should you equate or compare to solve the problem?
B
Step-by-Step Solution
Key idea: This is a checklist trigger question for work problems with changing group sizes and hours.
Step 1: When both the number of people and the hours per day change, the individual daily rates are no longer constant.
Step 2: The most reliable invariant to track is the total effort expended, measured in person-hours (or man-hours).
Step 3: You equate the person-hours used in each phase to the fraction of work completed in that phase.
Trap: Students sometimes try to track "mandays" but forget that the hours per day have changed, making "mandays" invalid unless hours are constant.
Answer: B