chapter

    Time, Work, Pipes and Productivity Pyqs for Cat

    Solve 15+ Time, Work, Pipes and Productivity previous year questions for CAT with answers and detailed solutions. Free sample questions below.

    Try a question

    Answer it here to see how it works. Nothing is recorded until you sign in.

    Question 1
    2025 Slot 3 PYQ
    Level 3: Exam Standard

    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a team is equally productive. Working separately, teams A, B, and C can complete a certain job in 40 hours, 50 hours, and 4 hours, respectively. Two members from team A, three members from team B, and one member from team C together start the job, and the member from team C leaves after 23 hours. The number of additional member(s) from team B, that would be required to replace the member from team C, to finish the job in the next one hour, is

    Question 2
    2025 Slot 2 PYQ
    Level 3: Exam Standard

    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start together on a job, and Bipin leaves the job after 20 days. If the job got completed in 60 days, the number of days needed by Chandan to complete the job alone, is

    Question 3
    2024 Slot 3 PYQ
    Level 3: Exam Standard

    Sam can complete a job in 20 days when working alone. Mohit is twice as fast as Sam and thrice as fast as Ayna in the same job. They undertake a job with an arrangement where Sam and Mohit work together on the first day, Sam and Ayna on the second day, Mohit and Ayna on the third day, and this three-day pattern is repeated till the work gets completed. Then, the fraction of total work done by Sam is

    Question 4
    2024 Slot 2 PYQ
    Level 3: Exam Standard

    Amal and Vimal together can complete a task in 150 days, while Vimal and Sunil together can complete the same task in 100 days. Amal starts working on the task and works for 75 days, then Vimal takes over and works for 135 days. Finally, Sunil takes over and completes the remaining task in 45 days. If Amal had started the task alone and worked on all days, Vimal had worked on every second day, and Sunil had worked on every third day, then the number of days required to complete the task would have been

    Question 5
    2024-Part-1 PYQ
    Level 3: Exam Standard

    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is

    Question 6
    2023 Slot 3 PYQ
    Level 3: Exam Standard

    Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is

    Question 7
    2023 Slot 2 PYQ
    Level 4: Challenger

    Pipes A and C are fill pipes while Pipe B is a drain pipe of a tank. Pipe B empties the full tank in one hour less than the time taken by Pipe A to fill the empty tank. When pipes A, B and C are turned on together, the empty tank is filled in two hours. If pipes B and C are turned on together when the tank is empty and Pipe B is turned off after one hour, then Pipe C takes another one hour and 15 minutes to fill the remaining tank. If Pipe A can fill the empty tank in less than five hours, then the time taken, in minutes, by Pipe C to fill the empty tank is

    Question 8
    2023 Slot 1 PYQ
    Level 3: Exam Standard

    The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number of days Sunil will take to finish the job working alone, is

    Question 9
    2022 Slot 2 PYQ
    Level 3: Exam Standard

    Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is

    Question 10
    2021 Slot 3 PYQ
    Level 3: Exam Standard

    Anil can paint a house in 12 days while Barun can paint it in 16 days. Anil, Barun, and Chandu undertake to paint the house for ₹ 24000 and the three of them together complete the painting in 6 days. If Chandu is paid in proportion to the work done by him, then the amount in INR received by him is

    Free preview ends here

    Login to view the complete previous-year questions and solutions

    Creating an account is free. You get the rest of this chapter, step-by-step solutions, and a study plan built around the topics you are actually weak at.

    Explore complete test series, official past papers, and chapter-wise study tools.

    Why MastersUp

    Personalised first. High quality throughout.

    Most platforms hand everyone the same content. Here the content moves with your performance, topic by topic.

    Built around you, not around a syllabus PDF

    Every answer you give moves your topic-level intelligence rate. The next question, the next revision card and tomorrow's plan all change with it.

    Revision that hits your weak spots

    We only revise topics you have actually attempted and are still below the safe bar on — never the same chapter on repeat.

    Questions calibrated to the real exam

    Each question carries a measured toughness. You are served a rung above your current level, so practice keeps stretching you.

    Notes written for recall, not for volume

    Full lesson cards for first study, curated short-note cards for the last mile — with derivations, traps and exam patterns marked.

    One place for everything

    Notes, chapter practice, previous-year questions, test series and full-length papers — all feeding one picture of your preparation.

    Honest progress

    No vanity streaks. Progress here means chapters mastered and accuracy that held up on harder questions.

    Unlock the whole course

    Full notes and short notes, the complete question bank with worked solutions, mock tests, full-length papers, and an adaptive plan that rebuilds itself as you improve.

    Time, Work, Pipes and Productivity PYQs for CAT

    Solve 15+ Time, Work, Pipes and Productivity previous year questions for CAT with answers and detailed solutions. Free sample questions below.

    Chapter Roadmap: Time, Work, Pipes and Productivity

    ⚙️
    Chapter Journey

    Time, Work, Pipes and Productivity

    Step 1 • 11 CAT PYQs • Importance 0.75

    👷 Work Rates and Efficiency

    Master work units, rates, efficiency ratios, groups, partial work, and replacement logic.

    Step 2 • 3 CAT PYQs • Importance 0.35

    🔁 Alternating Work and Rosters

    Handle day-wise cycles, alternate-day work, rotating pairs, and leftover work.

    Step 3 • 3 CAT PYQs • Importance 0.35

    💰 Payments, Wages and Cost Optimization

    Split wages by work done and choose efficient worker combinations under cost constraints.

    Step 4 • 3 CAT PYQs • Importance 0.35

    🚰 Pipes, Tanks and Drains

    Convert filling and emptying into positive and negative work rates.

    By the end of this chapter: you should be able to convert every worker, pipe, or team into a rate and add their contributions cleanly.

    Work Rates and Efficiency

    Arithmetic → Time, Work, Pipes and Productivity → Topic 1

    Work Rates and Efficiency

    The whole topic is one idea: work completed equals rate multiplied by time.

    R×T
    Work rate
    Efficiency ratios
    Man-hours
    Team productivity

    Time, Work, Pipes and Productivity: Solved Questions with Step-by-Step Explanations (10 Problems)

    Question 1 · Quantitative Ability · 2025 Slot 3 MCQ

    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a team is equally productive. Working separately, teams A, B, and C can complete a certain job in 40 hours, 50 hours, and 4 hours, respectively. Two members from team A, three members from team B, and one member from team C together start the job, and the member from team C leaves after 23 hours. The number of additional member(s) from team B, that would be required to replace the member from team C, to finish the job in the next one hour, is

    1. A.

      4

    2. B.

      2

    3. C.

      1

    4. D.

      3

    Correct Answer:

    B

    Step-by-Step Solution

    Key idea: this is a per-person productivity question, recognisable because teams have different member counts and each member within a team has equal productivity.

    Step 1: Find one member's rate for each team.

    Step 2: Team A has 5 members and completes the job in 40 hours. So team A's rate is:

    One A member's rate is:

    Step 3: Team B has 8 members and completes the job in 50 hours. So team B's rate is:

    One B member's rate is:

    Step 4: Team C has 10 members and completes the job in 4 hours. So team C's rate is:

    One C member's rate is:

    Step 5: Use denominator 400 for easy calculation:

    Step 6: Initially, 2 A members, 3 B members, and 1 C member work. Their combined rate is:

    Step 7: They work for 23 hours, so work completed is:

    Step 8: Remaining work:

    Step 9: The C member leaves. The remaining group has 2 A members and 3 B members. Its rate is:

    Step 10: Let additional B members be added. Each B member contributes . The required rate for the next 1 hour is:

    Step 11: Set up the equation:

    Step 12: Solve:

    Answer: option B.

    Question 2 · Quantitative Ability · 2025 Slot 2 NAT

    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start together on a job, and Bipin leaves the job after 20 days. If the job got completed in 60 days, the number of days needed by Chandan to complete the job alone, is

    Correct Answer:

    340

    Step-by-Step Solution

    Key idea: this is an efficiency-ratio work question, recognisable because workers are described as multiples of each other's efficiency and one worker leaves during the job.

    Step 1: Let Chandan's work rate be job per day.

    Step 2: Bipin is twice as efficient as Chandan, so Bipin's rate is:

    Step 3: Ankita is twice as efficient as Bipin, so Ankita's rate is:

    Step 4: All three start together. Their combined rate for the first 20 days is:

    Step 5: Work done in the first 20 days:

    Step 6: Bipin leaves after 20 days. The job is completed in 60 days, so the remaining time is:

    Step 7: For the remaining 40 days, only Ankita and Chandan work. Their combined rate is:

    Step 8: Work done in the remaining 40 days:

    Step 9: Total work:

    Step 10: Chandan alone works at rate , so time taken by Chandan alone is:

    Answer: $340$.

    Question 3 · Quantitative Ability · 2024 Slot 3 MCQ

    Sam can complete a job in 20 days when working alone. Mohit is twice as fast as Sam and thrice as fast as Ayna in the same job. They undertake a job with an arrangement where Sam and Mohit work together on the first day, Sam and Ayna on the second day, Mohit and Ayna on the third day, and this three-day pattern is repeated till the work gets completed. Then, the fraction of total work done by Sam is

    1. A.

    2. B.

    3. C.

    4. D.

    Correct Answer:

    B

    Step-by-Step Solution

    Key idea: This is a three-day pair roster question, recognisable because three workers rotate in pairs across a repeating 3-day cycle, and we need one worker's fraction of total work.

    Why this method: We compute work done per cycle, find how many full cycles fit, then handle the leftover day by day to get each worker's exact contribution.

    Step-by-step working:

    1. Find individual rates:
    • Sam: per day
    • Mohit is twice as fast as Sam: per day
    • Mohit is thrice as fast as Ayna: Ayna = per day
    1. Compute daily work in the cycle:
    • Day 1 (Sam + Mohit):
    • Day 2 (Sam + Ayna):
    • Day 3 (Mohit + Ayna):
    1. Work per 3-day cycle:
    1. Find full cycles and remainder:
    • full cycles + remainder
    • After 2 cycles: work done =
    • Remaining =
    1. Handle leftover (Day 7, 8, 9):
    • Day 7: Sam+Mohit do . Remaining was . After Day 7: left.
    • Day 8: Sam+Ayna do . After Day 8: left.
    • Day 9: Mohit+Ayna do . Work finishes during Day 9.
    1. Calculate Sam's total work:
    • In each cycle, Sam works Days 1 and 2:
    • 2 full cycles:
    • Day 7: Sam contributes
    • Day 8: Sam contributes
    • Day 9: Sam does not work
    • Sam's total =

    Answer: The fraction of total work done by Sam is .

    Question 4 · Quantitative Ability · 2024 Slot 2 NAT

    Amal and Vimal together can complete a task in 150 days, while Vimal and Sunil together can complete the same task in 100 days. Amal starts working on the task and works for 75 days, then Vimal takes over and works for 135 days. Finally, Sunil takes over and completes the remaining task in 45 days. If Amal had started the task alone and worked on all days, Vimal had worked on every second day, and Sunil had worked on every third day, then the number of days required to complete the task would have been

    Correct Answer:

    139

    Step-by-Step Solution

    Key idea: this is a pair-rate handover and roster question, recognisable because pair completion times are given, then one-by-one work durations reveal individual rates, and finally a periodic working pattern is asked.

    Step 1: Let Amal's rate be , Vimal's rate be , and Sunil's rate be , measured in jobs per day.

    Step 2: Amal and Vimal together complete the task in 150 days:

    Step 3: Vimal and Sunil together complete the task in 100 days:

    Step 4: In the actual handover, Amal works 75 days, Vimal works 135 days, and Sunil works 45 days, completing 1 job:

    Step 5: From the pair equations:

    Step 6: Substitute into the handover equation:

    Step 7: Simplify constants:

    So:

    Step 8: Combine terms:

    Step 9: Solve for :

    Step 10: Find and :

    Step 11: In the hypothetical pattern, Amal works every day, Vimal works every second day, and Sunil works every third day.

    Step 12: By day , Amal works days, Vimal works days, and Sunil works days.

    Step 13: Total work done by day :

    Step 14: For completion, multiply by 300:

    Step 15: Test near the expected value. For :

    Step 16: For :

    Therefore, the task is completed exactly at the end of day 139.

    Answer: $139$.

    Question 5 · Quantitative Ability · 2024 Part 1 NAT

    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is

    Correct Answer:

    6

    Step-by-Step Solution

    This is a man-hours with different hourly rates work problem. Recognise it because Renu and Seema have different individual rates of work per hour, and the question links their working hours per day and number of days together with ratios ("double the hours", "double the days") rather than giving them directly.

    Step 1 — find each person's rate of work per hour.

    Renu completes the task in 15 days at 4 hours/day, so her total work-hours for the whole task are hours. Her rate is:

    Seema completes the task in 8 days at 5 hours/day, so her total work-hours are hours. Her rate is:

    Step 2 — set up the joint working conditions.

    Renu works 2 hours/day (given). Seema works double the hours per day as Renu:

    Let Seema work days. Renu works double the number of days as Seema:

    Step 3 — write each person's total work contribution.

    Step 4 — total work equals 1 completed task.

    Using LCM 30:

    Step 5 — verify.

    Seema works days at 4 hours/day = 24 hours total; her work . Renu works days at 2 hours/day = 24 hours total; her work . Sum ✓ — the task is exactly completed.

    Trap: it's tempting to assume "double the hours" and "double the days" both apply to the same person's baseline, but they actually cross-reference each other (Seema's hours depend on Renu, Renu's days depend on Seema) — read each relationship carefully and assign the variable to the quantity given directly (Seema's days, since Renu's days is derived from it).

    The final answer is 6 days.

    Question 6 · Quantitative Ability · 2023 Slot 3 NAT

    Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is

    Correct Answer:

    36

    Step-by-Step Solution

    Key idea: This is a compensation condition reveals rate ratio question, recognisable because one worker reducing output forces the other to increase output to maintain the same combined rate.

    Why this method: The combined daily output must stay the same. The compensation condition gives a second equation linking the two rates, letting us find each rate individually.

    Step-by-step working:

    1. Define rates:
    • Let Gautam's daily rate = , Suhani's daily rate =
    • Together: ... (1)
    1. Apply the compensation condition:
    • Gautam at 60% + Suhani at 150% = same total output
    • ... (2)
    1. Solve for individual rates:
    • From (2):
    • Substitute into (1):
    1. Find time for each worker alone:
    • Gautam alone: days
    • Suhani alone: days
    1. Identify the faster worker:
    • Gautam (36 days) is faster than Suhani (45 days)

    Answer: The faster worker (Gautam) takes 36 days to complete the job alone.

    Question 7 · Quantitative Ability · 2023 Slot 2 MCQ

    Pipes A and C are fill pipes while Pipe B is a drain pipe of a tank. Pipe B empties the full tank in one hour less than the time taken by Pipe A to fill the empty tank. When pipes A, B and C are turned on together, the empty tank is filled in two hours. If pipes B and C are turned on together when the tank is empty and Pipe B is turned off after one hour, then Pipe C takes another one hour and 15 minutes to fill the remaining tank. If Pipe A can fill the empty tank in less than five hours, then the time taken, in minutes, by Pipe C to fill the empty tank is

    1. A.

      90

    2. B.

      120

    3. C.

      75

    4. D.

      60

    Correct Answer:

    A

    Step-by-Step Solution

    Key idea: This is a fill pipes, drain pipe, and switch-off question, recognisable because multiple pipes with different roles operate under different timing scenarios, giving equations to find individual rates.

    Why this method: Each scenario gives one equation in the pipe rates. We solve the system, then use the constraint on Pipe A's time to select the valid solution.

    Step-by-step working:

    1. Define rates:
    • Pipe A fills in hours: rate =
    • Pipe B empties in hours: rate =
    • Pipe C fills in hours: rate =
    1. Equation from scenario 1 (A, B, C together fill in 2 hours):
    • ... (1)
    1. Equation from scenario 2 (B and C for 1 hour, then C alone for 1.25 hours):
    • ... (2)
    1. Simplify equation (1):
    • ... (1')
    1. From equation (2):
    • ... (2')
    1. Set (1') = (2') and solve:
    • Multiply by :
    • or
    1. Apply constraint :
    1. Find :
    • From (2'):
    • hours = 90 minutes

    Answer: Pipe C takes 90 minutes to fill the empty tank.

    Question 8 · Quantitative Ability · 2023 Slot 1 NAT

    The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number of days Sunil will take to finish the job working alone, is

    Correct Answer:

    27

    Step-by-Step Solution

    This is a work rates in harmonic progression problem — recognisable because the question explicitly says the daily work amounts are in HP, and separately gives a time relationship plus partial-work data to find someone's solo time.

    Step 1: Understand what HP of rates means.

    Let Amal, Sunil, Kamal's daily work rates be , , (job done per day). "Rates in HP" means their reciprocals are in AP (arithmetic progression) — this is the definition of HP.

    Step 2: Use "Kamal takes twice as much time as Amal".

    Time is the reciprocal of rate, so:

    Step 3: Apply the AP condition to find .

    Since are in AP:

    Step 4: Compute the total work done from the given days.

    Total work:

    Step 5: Find the number of days Sunil alone needs.

    Answer: 27 days.

    Common trap: applying the HP condition directly to the rates as if they were in AP (instead of their reciprocals) — this changes the relationship between , , and and leads to a wrong value of .

    Question 9 · Quantitative Ability · 2022 Slot 2 NAT

    Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is

    Correct Answer:

    6

    Step-by-Step Solution

    Key idea: this is a work-rate and efficiency question. The trigger is that individual completion times are given in a ratio, and later the number of hours per day changes. We should convert time ratio into rate ratio and use work units.

    Step 1: Convert time ratio into rate ratio.

    Times taken by Anu, Tanu and Manu are in the ratio .

    Rate is inversely proportional to time.

    So their rates are proportional to:

    .

    Multiply by 40:

    .

    Let their hourly rates be 8, 5 and 4 work units per hour.

    Step 2: Find total work.

    All three together have rate:

    units per hour.

    They finish the job in 4 days, working 8 hours per day.

    Total hours together = hours.

    Total work = units.

    Step 3: Find work done by Anu and Tanu.

    Anu and Tanu together have rate:

    units per hour.

    They work for 6 days, 6 hours 40 minutes per day.

    Convert 6 hours 40 minutes:

    $40$ minutes = hour.

    So daily hours = hours.

    Total hours for 6 days:

    hours.

    Work done by Anu and Tanu:

    units.

    Step 4: Find remaining work.

    Remaining work = units.

    Step 5: Find Manu’s time for the remaining work.

    Manu’s rate is 4 units per hour.

    Time = hours.

    Answer: 6.

    Question 10 · Quantitative Ability · 2021 Slot 3 NAT

    Anil can paint a house in 12 days while Barun can paint it in 16 days. Anil, Barun, and Chandu undertake to paint the house for ₹ 24000 and the three of them together complete the painting in 6 days. If Chandu is paid in proportion to the work done by him, then the amount in INR received by him is

    Correct Answer:

    3000

    Step-by-Step Solution

    Key idea: this is a payment-by-work-share question. The trigger is “paid in proportion to the work done”. So we must find each painter’s fraction of the total work, not split the money equally.

    Step 1: Convert individual completion times into daily work rates.

    Anil can paint the house in 12 days, so Anil’s rate is:

    Barun can paint it in 16 days, so Barun’s rate is:

    Step 2: Use the team completion time.

    All three together complete the house in 6 days, so their combined rate is:

    Step 3: Find Chandu’s rate.

    Let Chandu’s rate be .

    So:

    Use denominator 48:

    Thus Chandu can paint of the house per day.

    Step 4: Find Chandu’s work done in 6 days.

    Since all three worked for 6 days:

    Step 5: Pay Chandu in proportion to his work.

    Total payment is ₹24000.

    Chandu’s share:

    Answer: 3000.

    Common trap: dividing ₹24000 equally among the three workers. Payment is proportional to work done, and Chandu’s contribution is only of the job.

    More previous year questions (pyqs) in this unit