Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is
6
Step-by-Step Solution
This is a man-hours with different hourly rates work problem. Recognise it because Renu and Seema have different individual rates of work per hour, and the question links their working hours per day and number of days together with ratios ("double the hours", "double the days") rather than giving them directly.
Step 1 — find each person's rate of work per hour.
Renu completes the task in 15 days at 4 hours/day, so her total work-hours for the whole task are hours. Her rate is:
Seema completes the task in 8 days at 5 hours/day, so her total work-hours are hours. Her rate is:
Step 2 — set up the joint working conditions.
Renu works 2 hours/day (given). Seema works double the hours per day as Renu:
Let Seema work days. Renu works double the number of days as Seema:
Step 3 — write each person's total work contribution.
Step 4 — total work equals 1 completed task.
Using LCM 30:
Step 5 — verify.
Seema works days at 4 hours/day = 24 hours total; her work . Renu works days at 2 hours/day = 24 hours total; her work . Sum ✓ — the task is exactly completed.
Trap: it's tempting to assume "double the hours" and "double the days" both apply to the same person's baseline, but they actually cross-reference each other (Seema's hours depend on Renu, Renu's days depend on Seema) — read each relationship carefully and assign the variable to the quantity given directly (Seema's days, since Renu's days is derived from it).
The final answer is 6 days.